Live Help

Email

Client portal

  • [ID Server] Server relocation in IDC D3 - 20 Jul 2018 - 10PM SGT

    July 19, 2018 by Tech #1
  • Dear Customers,

    As precaution measure from previous event, we have decided to relocate our ID server into different rack using different UPS cluster. This is taken because during the power surge, only this UPS cluster zone is affecting the IDC D3 Winter, but not other zone.

    The activity will be performed on 20th July 2018 at 10 PM SGT and expected downtime is about 1 hour.

    We apologize for the inconvenience caused.

    Thank you

    SOSYS.NET

    ===============

    20 Jul - 10PM: Server is shutdown and being unracked

    20 Jul - 11PM: Server is powered on in Spring zone

    20 Jul - 11.30PM: Configuration of the network in progress

    20 Jul - 11.55PM: Maintenance completed. All server is back to normal


cPanel Partner NOC